Copy subtasks from one task to another


#1

Since we provide our products in 12 languages, our translation team gets involved at some point in every project.

Currently we have a subtask or task called “Translate” somewhere in nearly every project. Under “Translate” there are subtasks for each translator. It would be great if I had a “Translate” task template with all the subtasks that I could drop into a project or task.

Is that possible?


#2

Hey @Bob_McNeel; Michael from Asana here.

This is a great idea! At the moment we only have the ability to create a template at the Project level. However as a workaround I encourage you to make a copy of your Translate Task, ensuring the subtask box is checked in the popup window that appears when you copy your Task. Once the copy has been created, multi-home the copied Task into your new Project. Once this copy has been added to the Project (Tab+P) then remove it from the Original Project so that the copied Translate Task only “lives” in your new Project exclusively.

The process of multihoming the Task into your new Project, and removing it from the first Project you copied it from feel like an additional step, however it will still save you the time & effort of creating a new Task with all it’s necessary subtasks from scratch. Additionally, if you create a template with this Translate Task already present, all Projects you make a copy of containing this Translate Task, will copy over in all your subsequent Projects.

That said, the ability to make a Task Template is an interesting idea I encourage you to post for in your #productfeedback category for our developers to look at & consider the viability of in the future.

Hope this makes sense!


#3

Hi Bob,
In addition to what Michael said, once your former template task “Translate” lives in your new project you can also transform it into a subtask with drag and drop.

@Alexis explained here how to do it.

Best
Sebastian


#4

Yes. I saw that. It was helpful. I came up with a workaround based on some of those ideas.

I’m not sure my suggestion is the best solution, but it seems like it would be nice to have a way to copy and move a task (with our without subtasks) or group of tasks in one step.

Drag with copy might be a solution. Right drag or drag with a modifier key… something like that might do the trick.

Also, I might just be using Asana all wrong. Under the Marketing Team, I have just the major projects like Blog, eNewsletter, etc. Under those, each blog post or eNewsletter is a task with subtasks. Maybe it would work better is each blog post, eNewsletter, etc. was a new project.

I thought it would work better as tasks since each blog post, newsletter, etc has a very short turn around. Often less than 3 days, including writing, layout, proofing, translation, etc.

I’m just thinking out loud here… aka babbling.