I’m a web designer and my projects typically need to be worked on for a couple weeks at a time. The way Asana lets me put in due dates now, they sneak up. If there could be a span of dates a project is needs to be worked on (like May 5th-16th) vs just due dates it would help me and my team tremendously!
7 Likes
This is one of the most common feature requests, and Asana has said they’re starting to explore how to implement start dates (which hopefully will lead to ranges). One workaround in the meantime is to create a task called “Start working on this,” and for the due date put the start date you would have put for the range.