Hi there,
I want to use several project templates that I can kick off whenever such a project is started. In these templates there are already assigned activities because these persons always execute these tasks. The thing is that as soon as I assign such a task to a person it is also visible in his/her tasks
I would like to mark a project as “template” so that the activities don’t show up in the assignees tasks.
Hope someone (or Asana) can help

1 Like

Hi @Roy_Slangen

This topic was already covered here: Project Template assigned tasks show up in My Tasks automatically

It might be worth having a read through the comments, especially @LenSantos’s suggestion.

1 Like

Thanks Mark, Allen’s hack works, but Patricio’s solution is better. For now it will do, thanks for your directions.